Density Test Report

Date :01/14/2026
Project No :2025C211
Client Company :Pulte
Arrival Time :01/14/2026 07:30
Onsite Hours :08:00
Name of the Project :Haley's Bluff - Philadelphia Rd.
Project Location :Jasper
Weather :Sunny
Departure Time :01/14/2026 15:30
ASEC Technician Name :Sean Willett

Observations/Finding

Test Date Test Number Moisture Content (%) Dry Density (pcf) Proctor Number Max. Dry Density (pcf) Optimum Moisture (%) Compaction (%) Specified Compaction (%) ASTM Test Method Pass/Fail
01/14/2026 1 21.6 97.0 FP 2 100.0 18.5 97.0 98 D6938 Fail
Location : Pipeline 2.0 to 2.1, Elv/Depth :at finished grade
Comment : contractor will recompact again and will retest on a later date Gauge Serial No. :77-19952
Technician Signature / DateSean Willett, January 14, 2026
Reviewer Name / DateKenneth Mosman, February 04, 2026