Skip to content

Daily Field Report

Date :02/19/2026
Project No :2026C103
Client Company :Artisan
Arrival Time :02/19/2026 09:00
Onsite Hours :9:00
Name of the Project :NW PH 2, UNIT 4
Project Location :Dallas
Weather :sunny
Departure Time :02/19/2026 18:00
ASEC Technician Name :Clyde Smith

Observations/Finding

As requested, the site was visited by our AS Engineering and Consulting (ASEC) representative for the purpose of providing quality control inspection and testing services.  Visual observation techniques were employed to verify compliance with project drawing/specifications, applicable codes, and materials submittals. The following observations were observed on site this day.

On the above date our representative was on site to observe the grading contractor continue breaking rock using a single tooth ripper at building Lots #42 and 43 and placing fill for Lots #63 thru 66. The writer performed density tests using a Troxler Nuclear gauge model 3430, serial no. 01643. The contractor spent approximately 4.5 hours using a ripper to break up rock today.

The pipe contractor continued backfilling an 8″ sanitary sewer line added between manholes #9 and 9.1 which was observed and tested by our representative. Compaction results were found to meet job specifications.

The water line contractor also continued installing 12″ ductile iron water line at Nature Walk Boulevard between manholes #4 and 6. The writer also observed placed concrete at the water vale box installed for the kicker. The backfill was probed using a rounded end steel rod and appeared compacted as per job standards.

We appreciate the opportunity to be of service to you on this project. If you have any questions regarding this report, please feel free to contact us. We will be more than happy to discuss it with you.

Backfilling at 8" sanitary sewer between manhole # 9 and 9-1

Using ripper to break rock

Placing fill at lots# 63 thru 66

Performing density tests at lots

Installation of 12" water line at Nature Walk blvd.

Backfill and compacting at 8" sanitary sewer between manhole # 9 and 9.1

Installation of 12" water line at Nature walk blvd.

Compacting efforts at building lots # 63 thru 66

Technician Signature / DateClyde Smith, February 19, 2026
Reviewer Name / DateKenneth Mosman, February 26, 2026