Daily Field Report

Date :03/05/2026
Project No :2026C101
Client Company :Artisan
Arrival Time :03/05/2026 11:30
Onsite Hours :01:00
Name of the Project :Seven Hills PHASE 13, UNIT 4 Lots
Project Location :Dallas
Weather :sunny
Departure Time :03/05/2026 12:30
ASEC Technician Name :Clyde Smith

Observations/Finding

As requested, the site was visited by our AS Engineering and Consulting (ASEC) representative for the purpose of providing quality control inspection and testing services.  Visual observation techniques were employed to verify compliance with project drawing/specifications, applicable codes, and materials submittals. The following observations were observed on site this day.

Our representative was on site to observe the grading contractor continue to excavate for the detention pond. The contractor stated that no density testing would be needed today and was asked to call when areas were ready to be tested. Contact information was left with contractor.

We appreciate the opportunity to be of service to you on this project. If you have any questions regarding this report, please feel free to contact us. We will be more than happy to discuss it with you.

Technician Signature / DateClyde Smith, March 5, 2026
Reviewer Name / DateKenneth Mosman, March 11, 2026