Skip to content

Daily Field Report

Date :03/06/2026
Project No :2026C103
Client Company :Artisan
Arrival Time :03/06/2026 07:30
Onsite Hours :07:30
Name of the Project :NW PH 2, UNIT 4
Project Location :Dallas
Weather :sunny
Departure Time :03/06/2026 15:00
ASEC Technician Name :Clyde Smith

Observations/Finding

On the above date the writer was onsite as requested and observed the Pipe contractor continue excavating between manhole # B-4 and B-5 to install 8″ pvc sanitary sewer line.Also continued backfilling sanitary sewer line between B-3 and B-5.

The Blast contractor also continued drilling at lots 43 and 42 planning for Blast on 3/9/26.

The Paving contractor also continued placing contract base stone at Nature Walk blvd. between manholes #6 and 9 over recommended repair sub grade areas.

Technician Signature / DateClyde Smith, March 6, 2026