Density Test Report

Date :03/21/2026
Project No :2025C211
Client Company :Pulte
Arrival Time :03/21/2026 08:00
Onsite Hours :03:00
Name of the Project :Haley's Bluff - Philadelphia Rd.
Project Location :Jasper
Weather :Sunny
Departure Time :03/21/2026 11:00
ASEC Technician Name :Sean Willett

Observations/Finding

Test Date Test Number Moisture Content (%) Dry Density (pcf) Proctor Number Max. Dry Density (pcf) Optimum Moisture (%) Compaction (%) Specified Compaction (%) ASTM Test Method Pass/Fail
03/21/2026 1 17.6 105.3 2025-055 107.3 15.5 98.1 95 D6938 Pass
Location : Retaining wall #1, Elv/Depth :5 baskets
Comment : Gauge Serial No. :77-19952
03/21/2026 2 16.5 99.0 FP 2 100.0 18.5 99.0 95 D6938 Pass
Location : Retaining wall #1, Elv/Depth :5 baskets
Comment : Gauge Serial No. :77-19952
03/21/2026 3 19.0 97.7 FP 2 100.0 18.5 97.7 95 D6938 Pass
Location : Retaining wall #1, Elv/Depth :5 baskets
Comment : Gauge Serial No. :77-19952
Technician Signature / DateSean Willett, March 21, 2026
Reviewer Name / DateKenneth Mosman, March 24, 2026