Density Test Report

Date :04/08/2026
Project No :2025C149
Client Company :Davidson Homes
Arrival Time :04/08/2026 08:00
Onsite Hours :06:00
Name of the Project :Grove at E. Thompson Mill Rd
Project Location :Buford
Weather :sunny
Departure Time :04/08/2026 14:00
ASEC Technician Name :Samara Simha Reddy Kandi

Observations/Finding

Test Date Test Number Moisture Content (%) Dry Density (pcf) Proctor Number Max. Dry Density (pcf) Optimum Moisture (%) Compaction (%) Specified Compaction (%) ASTM Test Method Pass/Fail
04/08/2026 1 24.4 87.5 2025-023 SP 103.5 18.9 84.5 95 D6938 Fail
Location : Lot #64, Elv/Depth :1030
Comment : Gauge Serial No. :91487
04/08/2026 2 17.2 95.4 2025-023 SP 103.5 18.9 92.2 95 D6938 Fail
Location : Lot #64, Elv/Depth :1030
Comment : Gauge Serial No. :91487
04/08/2026 3 18.9 92.5 2025-023 SP 103.5 18.9 89.4 95 D6938 Fail
Location : Lot #63, Elv/Depth :1028
Comment : Gauge Serial No. :91487
04/08/2026 4 17.7 92.8 2025-023 SP 103.5 18.9 89.7 95 D6938 Fail
Location : Lot #63, Elv/Depth :1028
Comment : Gauge Serial No. :91487
04/08/2026 5 15.5 93.4 2025-023 SP 103.5 18.9 90.2 95 D6938 Fail
Location : Lot #63, Elv/Depth :1026
Comment : Gauge Serial No. :91487
04/08/2026 6 18.4 90.7 2025-023 SP 103.5 18.9 87.6 95 D6938 Fail
Location : Lot #63, Elv/Depth :1026
Comment : Contractor removed top 6-8 inches, scarified, aerated and will re-compact. Gauge Serial No. :91487
Technician Signature / DateSamara Simha Reddy Kandi, April 8, 2026
Reviewer Name / DateKenneth Mosman, April 13, 2026