Density Test Report

Date :04/08/2026
Project No :2026C101
Client Company :Artisan
Arrival Time :04/08/2026 14:00
Onsite Hours :03:30
Name of the Project :Seven Hills PHASE 13, UNIT 4 Lots
Project Location :Dallas
Weather :sunny
Departure Time :04/08/2026 17:30
ASEC Technician Name :Samara Simha Reddy Kandi

Observations/Finding

Test Date Test Number Moisture Content (%) Dry Density (pcf) Proctor Number Max. Dry Density (pcf) Optimum Moisture (%) Compaction (%) Specified Compaction (%) ASTM Test Method Pass/Fail
04/08/2026 1 15.6 111.2 2025-031 SP 101.0 20.7 95.2 95 D6938 Pass
Location : Lot #41, Elv/Depth :3 feet below finished grade
Comment : Gauge Serial No. :91487
04/08/2026 2 15.9 111.9 2025-031 SP 101.0 20.7 95.5 95 D6938 Pass
Location : Lot #41, Elv/Depth :2.5 feet below finished grade
Comment : Gauge Serial No. :91487
04/08/2026 3 13.3 93.1 2025-032 SP 94.9 25.0 98.1 95 D6938 Pass
Location : Lot #42, Elv/Depth :3 feet below finished grade
Comment : Gauge Serial No. :91487
04/08/2026 4 15.2 102.1 2025-033 SP 104.0 16.2 98.2 95 D6938 Pass
Location : Lot #42, Elv/Depth :2.5 feet below finished grade
Comment : Gauge Serial No. :91487
Technician Signature / DateSamara Simha Reddy Kandi, April 8, 2026
Reviewer Name / DateKenneth Mosman, April 13, 2026