Daily Field Report

Date :04/08/2026
Project No :2025C216
Client Company :Artisan
Arrival Time :04/08/2026 07:00
Onsite Hours :03:00
Name of the Project :NW (Lots) Unit 4 PH 1A & 1B
Project Location :Dallas
Weather :Sunny
Departure Time :04/08/2026 10:0
ASEC Technician Name :Clyde Smith

Observations/Finding

As requested, the site was visited by our AS Engineering and Consulting (ASEC) representative for the purpose of providing quality control inspection and testing services. Visual observation techniques were employed to verify compliance with project drawing/specifications, applicable codes, and materials submittals. The following observations were observed on site this day.

On the above date the writer was on site as requested and observed the paving contractor continue subgrade and subbase preparation at Unit 4, Phase 1B. Base stone was placed over recommended clipped subgrade areas and contract stone was placed and compacted in the other areas.

We appreciate the opportunity to be of service to you on this project. If you have any questions regarding this report, please feel free to contact us. We will be more than happy to discuss it with you.

Observing test proof roll of subbase

Subgrade prep. at cul de sac

Subbase prep. compacting in place base stone

Technician Signature / DateClyde Smith, April 8, 2026
Reviewer Name / DateKenneth Mosman, April 13, 2026