- Density Test Report Report ID: 93177
- Edit Download Report
Density Test Report
Date :04/20/2026
Project No :2026C101
Client Company :Artisan
Arrival Time :04/20/2026 08:00
Onsite Hours :03:30
Name of the Project :Seven Hills PHASE 13, UNIT 4 Lots
Project Location :Dallas
Weather :Sunny
Departure Time :04/20/2026 11:30
ASEC Technician Name :Clyde Smith
Observations/Finding
| Test Date | Test Number | Moisture Content (%) | Dry Density (pcf) | Proctor Number | Max. Dry Density (pcf) | Optimum Moisture (%) | Compaction (%) | Specified Compaction (%) | ASTM Test Method | Pass/Fail |
|---|---|---|---|---|---|---|---|---|---|---|
| 04/20/2026 | 1 | 15.4 | 96.4 | 2025-033 SP | 104.0 | 16.2 | 92.7 | 98 | D6938 | Fail |
| Location : | Sanitary sewer backfill between Z15 and Z16, Elv/Depth :2 feet below finished grade | |||||||||
| Comment : | Gauge Serial No. :91643 | |||||||||
| 04/20/2026 | 2 | 15.3 | 96.7 | 2025-033 SP | 104.0 | 16.2 | 93.0 | 98 | D6938 | Fail |
| Location : | Sanitary sewer line backfill between Z15 and Z16, Elv/Depth :2 feet below finished grade | |||||||||
| Comment : | Gauge Serial No. :91643 | |||||||||
| 04/20/2026 | 3 | 13.5 | 102.3 | 2025-035 SP | 107.8 | 13.0 | 94.9 | 98 | D6938 | Fail |
| Location : | Sanitary sewer line backfill between Z15 and Z16, Elv/Depth :2 feet below finished grade | |||||||||
| Comment : | Gauge Serial No. :91643 | |||||||||
Technician Signature / DateClyde Smith, April 20, 2026
Reviewer Name / DateKenneth Mosman, April 27, 2026