Density Test Report

Date :04/23/2026
Project No :2025C149
Client Company :Davidson Homes
Arrival Time :04/23/2026 8:00
Onsite Hours :9:00
Name of the Project :Grove at E. Thompson Mill Rd
Project Location :Buford
Weather :clear and sunny
Departure Time :04/23/2026 17:00
ASEC Technician Name :Narayana Ganesh Undavalli

Observations/Finding

Test Date Test Number Moisture Content (%) Dry Density (pcf) Proctor Number Max. Dry Density (pcf) Optimum Moisture (%) Compaction (%) Specified Compaction (%) ASTM Test Method Pass/Fail
04/23/2026 1 17.3 106.0 2025-022 SP 103.7 16.1 102.2 95 D6938 Pass
Location : Retaining wall 5, Elv/Depth :2 feet
Comment : Gauge Serial No. :91487
04/23/2026 2 16.5 108.2 2025-022 SP 103.7 16.1 104.3 95 D6938 Pass
Location : Retaining wall 5, Elv/Depth :2 feet
Comment : Gauge Serial No. :91487
Technician Signature / DateNarayana Ganesh Undavalli, April 23, 2026
Reviewer Name / DateKenneth Mosman, June 03, 2026