Density Test Report
Date :06/18/2026
Project No :2026C101
Client Company :Artisan
Arrival Time :06/18/2026 08:00
Onsite Hours :04:00
Name of the Project :Seven Hills PHASE 13, UNIT 4 Lots
Project Location :Dallas
Weather :Overcast
Departure Time :06/18/2026 12:00
ASEC Technician Name :Sean Willett
Observations/Finding
| Test Date | Test Number | Moisture Content (%) | Dry Density (pcf) | Proctor Number | Max. Dry Density (pcf) | Optimum Moisture (%) | Compaction (%) | Specified Compaction (%) | ASTM Test Method | Pass/Fail |
|---|---|---|---|---|---|---|---|---|---|---|
| 06/18/2026 | 1 | 20.5 | 98.8 | Field proctor #6 | 98.0 | 17.2 | 100.8 | 95 | D6938 | Pass |
| Location : | D-7 to D-8, Elv/Depth :2 to 3 feet over pipeline | |||||||||
| Comment : | Gauge Serial No. :77-19952 | |||||||||
| 06/18/2026 | 2 | 20.8 | 95.0 | Field proctor #6 | 98.0 | 17.2 | 96.9 | 95 | D6938 | Pass |
| Location : | D-7 to D-8, Elv/Depth :2 to 3 feet over pipeline | |||||||||
| Comment : | Gauge Serial No. :77-19952 | |||||||||
Technician Signature / DateSean Willett, June 18, 2026
Reviewer Name / DateKenneth Mosman, July 07, 2026