Density Test Report

Date :07/01/2026
Project No :2026C100
Client Company :Artisan
Arrival Time :07/01/2026 11:00
Onsite Hours :04:00
Name of the Project :Naturewalk PHASE 3 (PH 2 Extension) Lots
Project Location :Dallas
Weather :sunny
Departure Time :07/01/2026 15:00
ASEC Technician Name :Samara Simha Reddy Kandi

Observations/Finding

Test Date Test Number Moisture Content (%) Dry Density (pcf) Proctor Number Max. Dry Density (pcf) Optimum Moisture (%) Compaction (%) Specified Compaction (%) ASTM Test Method Pass/Fail
07/01/2026 1 18.1 95.3 Field proctor #6 98.0 17.2 97.2 95 D6938 Pass
Location : Lot #61, Elv/Depth :4 feet below finished grade
Comment : Gauge Serial No. :38069
07/01/2026 2 16.4 95.2 Field proctor #6 98.0 17.2 97.1 95 D6938 Pass
Location : Lot #61, Elv/Depth :4 feet below finished grade
Comment : Gauge Serial No. :38069
07/01/2026 3 24.6 92.5 2025-032 SP 94.9 25.0 97.5 95 D6938 Pass
Location : Lot #60, Elv/Depth :5 feet below finished grade
Comment : Gauge Serial No. :38069
07/01/2026 4 23.1 91.3 2025-032 SP 94.9 25.0 96.2 95 D6938 Pass
Location : Lot #60, Elv/Depth :5 feet below finished grade
Comment : Gauge Serial No. :38069
07/01/2026 5 14.5 95.0 Field proctor #6 98.0 17.2 96.9 95 D6938 Pass
Location : Lot #60, Elv/Depth :3 feet below finished grade
Comment : Gauge Serial No. :38069
07/01/2026 6 13.4 100.4 2025-033 SP 104.0 16.2 96.5 95 D6938 Pass
Location : Lot #60, Elv/Depth :3 feet below finished grade
Comment : Gauge Serial No. :38069
Technician Signature / DateSamara Simha Reddy Kandi, July 1, 2026
Reviewer Name / DateKenneth Mosman, July 08, 2026