Skip to content

Daily Field Report

Date :07/06/2026
Project No :2026C103
Client Company :Artisan
Arrival Time :07/06/2026 13:00
Onsite Hours :02:00
Name of the Project :NW PH 2, UNIT 4
Project Location :Dallas
Weather :sunny
Departure Time :07/06/2026 15:00
ASEC Technician Name :Samara Simha Reddy Kandi

Observations/Finding

As requested, the site was visited by our AS Engineering and Consulting (ASEC) representative for the purpose of providing quality control inspection and testing services. Visual observation techniques were employed to verify compliance with project drawing/specifications, applicable codes, and materials submittals. The following observations were observed on site this day.

At Road C, adjacent to Lot #28, the crew excavated a trench to the required depth and leveled the subgrade prior to pipe installation. Two parallel 4-inch PVC sewer service pipes, each approximately 30 lineal feet in length, were installed. At Lots #31 and 34, the crew installed one 4-inch PVC sewer service pipe for each lot. At Road D near Lot #56, one 4-inch PVC sewer service pipe was installed. At Lot #57, two 4-inch PVC sewer service pipes were installed parallel to each other. After installation, backfill material was placed around and above the pipes in lifts and compacted using a trench compactor. The upper portions of the backfill were further compacted using a sheep-foot roller.

We appreciate the opportunity to be of service to you on this project. If you have any questions regarding this report, please feel free to contact us. We will be more than happy to discuss it with you.

Technician Signature / DateSamara Simha Reddy Kandi, July 6, 2026
Reviewer Name / DateKenneth Mosman, July 30, 2026