Daily Field Report
Observations/Finding
As requested, the site was visited by our AS Engineering and Consulting (ASEC) representative for the purpose of providing quality control inspection and testing services. Visual observation techniques were employed to verify compliance with project drawing/specifications, applicable codes, and materials
submittals. The following observations were observed on site this day.
Our ASEC representative was on site to observe the contractor and for the observation/testing of the placement of fill/backfill. A proof-roll was performed on the GAB located around the grease traps in the middle of the site. There was no severe pumping present in this area. The contractors removed asphalt from the light duty road and there was pumping present under movement of a skid steer. It was recommended to remove the GAB and excavate approximately 2 feet to 3 feet of the soft soils and replace with GAB in approximately 8-inch lifts. The contractor agreed and fixed this area of the road. There was still a slight pumping present after fixing this area, but due to time restraints, and because it was a light duty road, the contractor decided to pave it. The contractors milled out the bad sections of the asphalt marked with green paint. Some areas appeared to be cracked or higher than 1.5 inches below the curbs. After milling, the contractor paved the milled areas as well as the GAB area around the grease traps in the middle of the site. Trucks were checked for temperatures, and the paving was observed by ASEC.
We appreciate the opportunity to be of service to you on this project. If you have any questions regarding this report, please feel free to contact us. We will be more than happy to discuss it with you.