Date :08/05/2026
Project No :2025C214
Client Company :Artisan
Arrival Time :08/05/2026 12:30
Onsite Hours :04:30
Name of the Project :NW Unit 4 BRIDGE (Materials Testing)
Project Location :Dallas
Weather :cloudy
Departure Time :08/05/2026 17:00
ASEC Technician Name :Clyde Smith

Observations/Finding

As requested, the site was visited by our AS Engineering and Consulting (ASEC) representative for the purpose of providing quality control inspection and testing services.  Visual observation techniques were employed to verify compliance with project drawing/specifications, applicable codes, and materials submittals. The following observations were observed on site this day.

On the above date our representative was onsite to observe the wall contractor RWS placing and compacting backfill at the bridge abutment between the bridge and dead man footing. The writer performed density tests using a Troxler nuclear gauge model 3430, serial no. 91643. Compaction results were in compliance with project specifications.

The writer observed the curbing contractor installing 30″ curbing for Naturewalk parkway between sanitary sewer manholes #14 and 13.

The grading contractor continued erosion repairs at unit 4 phase 3 and hauling fill materials to RWS for backfill at bridge abutment.

We appreciate the opportunity to be of service to you on this project. If you have any questions regarding this report, please feel free to contact us. We will be more than happy to discuss it with you.

Density tests performed at west side bridge abutment -10' below opening for sanitary sewer installation.

Hauled and placed stockpiled materials the contractor attempted to place as fill but was rejected due to moisture content and large boulders.

Hauled fill placement

Spreading and compacting fill at abutment

Technician Signature / DateClyde Smith, August 5, 2026
Reviewer Name / DateKenneth Mosman, August 11, 2026