Daily Field Report
Observations/Finding
As requested, the site was visited by our AS Engineering and Consulting (ASEC) representative for the purpose of providing quality control inspection and testing services. Visual observation techniques were employed to verify compliance with project drawing/specifications, applicable codes, and materials submittals. The following observations were observed on site this day.
On the above date our representative made two trips to observe fill placement for the bridge west side abutment in the morning and performing density tests late afternoon after compacting efforts had been complete. Compaction results failed to meet project specifications and recommendations were made to use an off-road dump truck for additional compacting efforts. The contractor plans to follow recommendations and re compact tomorrow prior to re-testing. Density tests were performed at elevation -7.5 feet below the sanitary sewer installation location.
We appreciate the opportunity to be of service to you on this project. If you have any questions regarding this report, please feel free to contact us. We will be more than happy to discuss it with you.

Performed density tests all areas failed

Density tests




Fill and compacting efforts observed

Tension rods observed at abutment wall


Fill placement at bridge abutment