Density Test Report

Date :08/11/2026
Project No :2026C101
Client Company :Artisan
Arrival Time :08/11/2026 07:30
Onsite Hours :04:00
Name of the Project :Seven Hills PHASE 13, UNIT 3 Lots
Project Location :Dallas
Weather :cloudy
Departure Time :08/11/2026 11:30
ASEC Technician Name :Clyde Smith

Observations/Finding

Test Date Test Number Moisture Content (%) Dry Density (pcf) Proctor Number Max. Dry Density (pcf) Optimum Moisture (%) Compaction (%) Specified Compaction (%) ASTM Test Method Pass/Fail
08/11/2026 1 23.2 90.6 2025-032 SP 94.9 25.0 95.5 95 D6938 Pass
Location : Building Lot #33, Elv/Depth :2.5 feet below finished grade
Comment : Gauge Serial No. :91643
08/11/2026 2 22.4 92.5 2025-032 SP 94.9 25.0 97.5 95 D6938 Pass
Location : Building Lot #33, Elv/Depth :2.5 feet below finished grade
Comment : Gauge Serial No. :91643
08/11/2026 3 14.0 101.1 2025-033 SP 104.0 16.2 97.2 95 D6938 Pass
Location : Building Lot #34, Elv/Depth :2.5 feet below finished grade
Comment : Gauge Serial No. :91643
08/11/2026 4 15.1 101.0 2025-033 SP 104.0 16.2 97.1 95 D6938 Pass
Location : Building Lot #34, Elv/Depth :2.5 feet below finished grade
Comment : Gauge Serial No. :91643
Technician Signature / DateClyde Smith, August 11, 2026
Reviewer Name / DateKenneth Mosman, August 19, 2026