Density Test Report

Date :08/13/2026
Project No :2025C214
Client Company :Artisan
Arrival Time :08/13/2026
Onsite Hours :
Name of the Project :NW Unit 4 BRIDGE (Materials Testing)
Project Location :Dallas
Weather :sunny
Departure Time :08/13/2026
ASEC Technician Name :Russell Hendrix

Observations/Finding

Test Date Test Number Moisture Content (%) Dry Density (pcf) Proctor Number Max. Dry Density (pcf) Optimum Moisture (%) Compaction (%) Specified Compaction (%) ASTM Test Method Pass/Fail
08/13/2026 1 17.3 100.0 North Bridge mixture 106.8 17.5 93.6 95 D6938 Fail
Location : North side 20 feet from wall, Elv/Depth :-4 feet
Comment : Mix of soils Gauge Serial No. :92204
08/13/2026 2 20.1 94.3 North Bridge mixture 106.8 17.5 88.3 95 D6938 Fail
Location : South side 10 feet from wall, Elv/Depth :-4 feet
Comment : mix of soils Gauge Serial No. :92204
Technician Signature / DateRussell Hendrix, August 13, 2026