- Home
- Daily Field Report Report ID: 96934
- Edit Download Report
Daily Field Report
Observations/Finding
As requested, the site was visited by our AS Engineering and Consulting (ASEC) representative for the purpose of providing quality control inspection and testing services. Visual observation techniques were employed to verify compliance with project drawing/specifications, applicable codes, and materials
submittals. The following observations were observed on site this day.
The crew commenced manhole installation and connection to a 12-inch corrugated drainpipe that extends from a concrete structure located at the surface level.
The placement of concrete then commenced around the manhole and pipe connection.
We appreciate the opportunity to be of service to you on this project. If you have any questions regardingthis report, please feel free to contact us. We will be more than happy to discuss it with you.