Daily Field Report

Date :08/18/2026
Project No :2026C101
Client Company :Artisan
Arrival Time :08/18/2026 07:30
Onsite Hours :07:00
Name of the Project :Seven Hills PHASE 13, UNIT 3 Lots
Project Location :Dallas
Weather :cloudy
Departure Time :08/18/2026 14:30
ASEC Technician Name :

Observations/Finding

As requested, the site was visited by our AS Engineering and Consulting (ASEC) representative for the purpose of providing quality control inspection and testing services.  Visual observation techniques were employed to verify compliance with project drawing/specifications, applicable codes, and materials submittals. The following observations were observed on site this day.

On the above date our representative was on site to observe the paving contractor J&W continue subgrade preparation for the roadway starting above the Plantation Gas lines to the cul-de-sac after a rain event late in the afternoon on 8/17/26. The contractor clipped an additional -2″ of existing subgrade saturated soils to be replaced with additional base stone. The contractor began placing base stone over approved subgrade soils pushing out over the subgrade as recommended.

The writer observed the grading contractor Thompson continue placing topsoil materials in thick lifts with minimum compacting efforts. The contractor was reminded that in the slope embankment compacting efforts are required. This material was being placed at elevation -12 feet.

The writer observed the wall contractor RWS continue placing fill at the bridge abutment with the grading contractor assisting by hauling materials and providing additional compacting efforts using a loaded off-road dump truck. The writer performed density tests using a Troxler Nuclear gauge model 3430, serial no. 91643. Compaction results were in compliance with job specifications.

The writer also observed the grading contractor Thompson continue placing fill at unit 4 phase 3 future lots. The contractor was placing fill soils containing large boulders and is requesting lot numbers or elevations to determine suitability of fill placement. The contractor was reminded that boulder fill should not be placed within the top four feet of finished subgrade for the building lot pads.

We appreciate the opportunity to be of service to you on this project. If you have any questions regarding this report, please feel free to contact us. We will be more than happy to discuss it with you.

Fill placement at Unit4 phase3 future lots with large boulders.

Fill placement at Unit 4 phase 3

Slope embankment fill at roadway near detention pond between B6 ST JB and B5 ST JB.Thick lift with limited compacting efforts

Fill placement at roadway

Sub base stone placement at roadway phase 13

Truck ticket with 18 plus tons for proof roll

Technician Signature / DateClyde Smith, August 18, 2026