As requested, the site was visited by our AS Engineering and Consulting (ASEC) representative for the purpose of providing quality control inspection and testing services. Visual observation techniques were employed to verify compliance with project drawing/specifications, applicable codes, and materials submittals. The following observations were observed on site this day.
A pre-pour inspection was performed on lane 2 with representatives from CW Matthews, QC, Holder, QA, and ATLNext present. The area was inspected, and all parties were in agreement that the work was suitable for concrete placement.
No further observations were made on this day.
We appreciate the opportunity to be of service to you on this project. If you have any questions regarding this report, please feel free to contact us. We will be more than happy to discuss it with you.