Daily Field Report

Date :09/15/2026
Project No :2026C101
Client Company :Artisan
Arrival Time :09/15/2026 07:30
Onsite Hours :10:00
Name of the Project :Seven Hills PHASE 13, UNIT 3 Lots
Project Location :Dallas
Weather :Sunny
Departure Time :09/15/2026 17:30
ASEC Technician Name :Clyde Smith

Observations/Finding

As requested, the site was visited by our AS Engineering and Consulting (ASEC) representative for the purpose of providing quality control inspection and testing services.  Visual observation techniques were employed to verify compliance with project drawing/specifications, applicable codes, and materials submittals. The following observations were observed on site this day.

On the above date our representative was on site to observe the grading contractor Thompson continue placing fill at building Lots #10 thru 14. The contractor began excavating a borrow pit to obtain fill materials for building lots. The borrow pit was located south of building Lot #24 near the slope embankment. The contractor plans to refill the excavated hole that is approximately over twenty feet deep.

The writer also observed curbing pour at Unit 4 phase 2 parking lot.

We appreciate the opportunity to be of service to you on this project. If you have any questions regarding this report, please feel free to contact us. We will be more than happy to discuss it with you.

Excavation of borrow pit south of building lot # 24

Placement of fill at building lots

Compacting efforts of fill placement

Pouring curbing at Unit 4 phase 2 parking lot

Location of excavated borrow pit

Technician Signature / DateClyde Smith, September 15, 2026
Reviewer Name / DateKenneth Mosman, September 17, 2026