Daily Field Report
Observations/Finding
As requested, the site was visited by our AS Engineering and Consulting (ASEC) representative for the purpose of providing quality control inspection and testing services. Visual observation techniques were employed to verify compliance with project drawing/specifications, applicable codes, and materials submittals. The following observations were observed on site this day.
On the above date our representative observed subgrade preparation and proof-rolling of subgrade soils for the west side of bridge between the bridge and roundabout. The subgrade was proof-rolled using a loaded tandem dump truck. The subgrade soils appeared stable under traffic and was approved for base stone placement. The paving contractor began placing base stone over the subgrade and continued fine grading and compacting for the east side of the bridge.
The grading contractor Thompson continued subgrade preparation and backfilling behind curbing at Unit 4 phase 2.
We appreciate the opportunity to be of service to you on this project. If you have any questions regarding this report, please feel free to contact us. We will be more than happy to discuss it with you.

Backfilling behind curbing and subgrade prep. at Unit 4 phase 2 by the Grading contractor



Subgrade prep.at Nature Walk Pkwy. to round about

Proof rolling of subgrade to round about