Daily Field Report

Date :10/12/2026
Project No :2025C215
Client Company :Artisan
Arrival Time :10/12/2026 07:30
Onsite Hours :9:00
Name of the Project :NW Unit 4 Parkway Ext. Phase 1
Project Location :Dallas
Weather :Sunny
Departure Time :10/12/2026 16:30
ASEC Technician Name :Clyde Smith

Observations/Finding

As requested, the site was visited by our AS Engineering and Consulting (ASEC) representative for the purpose of providing quality control inspection and testing services.  Visual observation techniques were employed to verify compliance with project drawing/specifications, applicable codes, and materials submittals. The following observations were observed on site this day.

On the above date our representative observed the paving contractor NWGP remove subbase stone at the westside curb roundabout to lower the subgrade. The grading contractor Thompson performed subgrade preparation lowering the subgrade from 11.5 ” to 14.5″ at the roundabout. The writer also attended a site meeting to discuss replacing type 7 curbing to type 9 curbing at the westside roundabout.

The pipe contractor Savannah completed repairs lowering sanitary sewer manholes at Unit 4, Phase 2.

The electrical contractor Mastec continued excavation and installing conduits at Unit 4, Phase 1B.

We appreciate the opportunity to be of service to you on this project. If you have any questions regarding this report, please feel free to contact us. We will be more than happy to discuss it with you.

Electrical contractor Mastec installing conduits

Subgrade prep at roundabout

Subgrade and subbase prep. at roundabout

Technician Signature / DateClyde Smith, October 12, 2026
Reviewer Name / DateKenneth Mosman, October 21, 2026