Skip to content
Menu
Home
About
Daily Field Report
Density Test Report
Concrete Test Report
Login
Home
About
Daily Field Report
Density Test Report
Concrete Test Report
Home
Daily Field Report
Density test report
Date
*
Project Number
*
2025C245(Dunkin Donuts 2025)
Name of the Project
*
Project Location
Client Company
*
Weather
Arrival Date
Arrival Time
Departure Date
Departure Time
Onsite Hours
ASEC Technician Name
sean.willett (Sean Willett)
Observations/Finding
Summary
*
<h3 data-start="670" data-end="694"><strong data-start="674" data-end="694">urpose of Visit</strong></h3> <p data-start="695" data-end="1044">As requested, an AS Engineering and Consulting (ASEC) representative visited the site to provide <strong data-start="792" data-end="843">quality control inspection and testing services</strong> related to <strong data-start="855" data-end="886">fill and backfill placement</strong>. Visual observation techniques were employed to verify compliance with project drawings, specifications, applicable codes, and approved materials submittals.</p> <hr data-start="1046" data-end="1049" /> <h3 data-start="1051" data-end="1077"><strong data-start="1055" data-end="1077">Field Observations</strong></h3> <p data-start="1078" data-end="1362">Density testing was performed along the <strong data-start="1118" data-end="1146">retaining wall alignment</strong>. Test results indicated <strong data-start="1171" data-end="1196">low compaction values</strong>, despite the soil being within its <strong data-start="1232" data-end="1258">optimum moisture range</strong>. This suggests that the lifts were not being adequately compacted before additional layers were placed.</p> <p data-start="1364" data-end="1658">ASEC recommended that the contractor maintain lift thicknesses between <strong data-start="1435" data-end="1454">8 and 12 inches</strong> and ensure each lift is properly compacted before placement of subsequent layers. The contractor was informed of the failing test results and advised to <strong data-start="1608" data-end="1618">reroll</strong> the deficient areas prior to retesting.</p> <p data-start="1660" data-end="2197">Although the contractor initially acknowledged the recommendation, they <strong data-start="1732" data-end="1774">did not compact the ground immediately</strong> and instead took a break. Shortly before our representative’s planned departure to deliver proctor samples to the laboratory, the contractor resumed rolling the failed areas approximately <strong data-start="1963" data-end="1987">three to four passes</strong> with a large sheep’s foot roller and requested retesting.<br data-start="2045" data-end="2048" />Despite the rerolling effort, <strong data-start="2078" data-end="2133">compaction results remained below acceptable levels</strong>, indicating inadequate compaction with the available equipment.</p> <hr data-start="2199" data-end="2202" /> <h3 data-start="2204" data-end="2235"><strong data-start="2208" data-end="2235">Contractor Coordination</strong></h3> <p data-start="2236" data-end="2513">Mr. <strong data-start="2240" data-end="2257">Jamie Jenkins</strong>, the wall contractor’s supervisor, was present during the inspection. ASEC’s representative informed Mr. Jenkins and his crew <strong data-start="2384" data-end="2437">multiple times (at least three to four occasions)</strong> that the area between the two manholes had <strong data-start="2481" data-end="2510">failed compaction testing</strong>.</p> <p data-start="2515" data-end="2995">Mr. Jenkins questioned why <strong data-start="2542" data-end="2577">Dynamic Cone Penetrometer (DCP)</strong> testing was not performed on the soil lifts. Our representative clarified that ASEC was <strong data-start="2666" data-end="2707">not contracted for footing inspection</strong> and that <strong data-start="2717" data-end="2789">DCP testing is not required for routine lift compaction verification</strong>. Mr. Jenkins appeared displeased with this explanation and responded in a disrespectful manner. He was informed that ASEC would return later in the day, at the contractor’s request, for additional testing.</p> <p data-start="2997" data-end="3118">Our representative subsequently departed the site and <strong data-start="3051" data-end="3082">delivered stockpile samples</strong> to the ASEC laboratory for testing.</p> <hr data-start="3120" data-end="3123" /> <h3 data-start="3125" data-end="3148"><strong data-start="3129" data-end="3148">Afternoon Visit</strong></h3> <p data-start="3149" data-end="3597">Upon returning to the site later that afternoon, ASEC’s representative observed that the <strong data-start="3238" data-end="3338">contractor had continued to place new lifts over areas that previously failed compaction testing</strong>, contrary to prior recommendations. When questioned, the contractor claimed that Mr. Jenkins was unaware of the failing areas; however, this was inaccurate, as both Mr. Jenkins and his crew had been <strong data-start="3538" data-end="3561">explicitly notified</strong> of the failures earlier in the day.</p> <p data-start="3599" data-end="3880">Rather than removing the noncompliant lifts, the contractor <strong data-start="3659" data-end="3720">continued fill placement and wall installation activities</strong>. It was also noted that lift thicknesses <strong data-start="3762" data-end="3794">appeared to exceed 12 inches</strong> and that compaction effort remained inadequate for the material and equipment in use.</p> <hr data-start="3882" data-end="3885" /> <h3 data-start="3887" data-end="3913"><strong data-start="3891" data-end="3913">Contractor Conduct</strong></h3> <p data-start="3914" data-end="4299">Mr. Jenkins’ demeanor toward ASEC’s representative has become increasingly <strong data-start="3989" data-end="4025">disrespectful and noncooperative</strong>. He subsequently contacted our representative by phone, using <strong data-start="4088" data-end="4124">foul and unprofessional language</strong>. ASEC reiterates that its field representatives are <strong data-start="4177" data-end="4212">not responsible for time delays</strong> related to other trades (e.g., pipe installation) or unsuitable material conditions.</p> <p data-start="4301" data-end="4575">ASEC’s scope of work is limited to <strong data-start="4336" data-end="4375">observation, testing, and reporting</strong>. Compaction rates and wall construction methods remain the <strong data-start="4435" data-end="4471">responsibility of the contractor</strong>. All test results and observations were properly communicated to site personnel at the time of testing.</p> <hr data-start="4577" data-end="4580" /> <h3 data-start="4582" data-end="4608"><strong data-start="4586" data-end="4608">Summary of Results</strong></h3> <ul data-start="4609" data-end="4984"> <li data-start="4609" data-end="4699"> <p data-start="4611" data-end="4699">Several test locations <strong data-start="4634" data-end="4660">failed density testing</strong> due to inadequate compaction effort.</p> </li> <li data-start="4700" data-end="4847"> <p data-start="4702" data-end="4847"><strong data-start="4702" data-end="4721">Passing results</strong> were obtained only in areas where the contractor placed <strong data-start="4778" data-end="4814">smaller lifts (6–8 inches thick)</strong> and adequately compacted them.</p> </li> <li data-start="4848" data-end="4984"> <p data-start="4850" data-end="4984">The contractor was repeatedly advised to maintain proper lift thickness and compaction practices to meet specification requirements.</p> </li> </ul> <hr data-start="4986" data-end="4989" /> <h3 data-start="4991" data-end="5006"><strong data-start="4995" data-end="5006">Remarks</strong></h3> <p data-start="5007" data-end="5226">ASEC will continue to monitor fill placement and compaction activities during subsequent site visits. Any additional deficiencies or deviations from specification will be documented and reported to the project engineer.</p> <hr data-start="5228" data-end="5231" /> <h3 data-start="5233" data-end="5251"><strong data-start="5237" data-end="5251">Conclusion</strong></h3> <p data-start="5252" data-end="5511">AS Engineering and Consulting, LLC appreciates the opportunity to provide our testing and inspection services on this project. Should you have any questions or require further clarification regarding this report, please contact our office at your convenience.</p>
Upload Images
Image
Description
1
2
3
4
1
Add Row
Post Status custom
Validate Email
Visual
Text
Insert/edit link
Close
Enter the destination URL
URL
Link Text
Open link in a new tab
Or link to existing content
Search
No search term specified. Showing recent items.
Search or use up and down arrow keys to select an item.
Cancel