Skip to content
Menu
Home
About
Daily Field Report
Density Test Report
Concrete Test Report
Login
Home
About
Daily Field Report
Density Test Report
Concrete Test Report
Home
Daily Field Report
Density test report
Date
*
Project Number
*
2026C103(NW PH 2, UNIT 4)
Name of the Project
*
Project Location
Client Company
*
Weather
Arrival Date
Arrival Time
Departure Date
Departure Time
Onsite Hours
ASEC Technician Name
clyde.smith (Clyde Smith)
Observations/Finding
Summary
*
As requested, the site was visited by our AS Engineering and Consulting (ASEC) representative for the purpose of providing quality control inspection and testing services. Visual observation techniques were employed to verify compliance with project drawing/specifications, applicable codes, and materials submittals. The following observations were observed on site this day. On the above date our representative was on site to observe the grading contractor continue placing fill for the slope embankment and building Lots #41 thru 37 and Lot#56. The writer also performed density tests using a Troxler Nuclear gauge model3430, serial no. 91743. Compaction results were in compliance with job specifications. The contractor also observed the blasting contractor who was on site performing rock test drill holes. The pipe contractor was on site continuing to install 30" RCP storm line between structures D9 and D10. Also continued 30" from D10 installing two joints of pipe. All pipe was bedded on residual soils or rock. The contractor continued washed silt clean up off the subbase stone at Naturewalk parkway between sanitary sewer manholes #6 and 9. We appreciate the opportunity to be of service to you on this project. If you have any questions regarding this report, please feel free to contact us. We will be more than happy to discuss it with you.
Upload Images
Image
Description
1
Performing density tests at lots 41 thru 37
2
3
4
Installation of 30"rcp storm between D9 and D10
5
Compacting efforts using 815 cat roller and off road dump truck
6
Washed silt after rain event covering sub base stone between sanitary sewer manhole #6 and 9.
7
Fill placement at lot #56
1
Add Row
Post Status custom
Validate Email
Visual
Code
Insert/edit link
Close
Enter the destination URL
URL
Link Text
Open link in a new tab
Or link to existing content
Search
No search term specified. Showing recent items.
Search or use up and down arrow keys to select an item.
Cancel