Skip to content

Daily Field Report

Date :05/21/2021
Project No :2021C048
Client Company :DR Horton West
Arrival Time :05/21/2021 08:00
Onsite Hours :06:00
Name of the Project :Tributary - Retaining Walls
Project Location :Douglasville, GA
Weather :Overcast
Departure Time :05/21/2021 14:00
ASEC Technician Name :Dave Bek

Observations/Finding

The site was visited by the undersigned AS Engineering and Consulting (ASEC) representative for the purpose of providing quality control inspection and testing services. Visual observation techniques were employed to assure compliance with project drawings/specifications, applicable codes, and materials submittals. The following observations were made on site today

Upon arrival to the site, the writer was informed by the site superintendent Victor that work was underway for the construction of a (approx) 9’ retaining wall on lot 228. The civil plans show plans for a 6’ wall, but Victor explained that it would require 3 additional feet to attain the level required.

A single Takeuchi mini excavator worked in tandem with a Takeuchi skid loader to excavate the retaining wall footing. The writer proceeded to the base of the footing and performed DCP tests along the excavation zone (the total length of the footing was approximately 40ft in length and 2 feet deep) The soil profile was saturated with rock fragments and roots making advancement with a hand-auger impractical. The DCP density test report for this day list the test results for the work performed on this day.

Work was slowed as the construction crew was experiencing mechanical difficulties with the Takeuchi mini excavator.

A geo-grid was brought in to be placed after 3 lifts of backfill and compaction (per Victor) the length was measured by the writer and found to be approximately 10 feet in total length (approx 110% of retaining wall height)

Footing Excavation Lot 228

Pre-excavation

Technician Signature / DateDave Bek, May 21, 2021
Reviewer Name / DateRamchandra Mogulla, July 28, 2021