- Daily Field Report Report ID: 26155
- This project is inactive from admin.Download Report
Daily Field Report
Observations/Finding
The site was visited by the undersigned AS Engineering and Consulting (ASEC) representative for the purpose of providing quality control inspection and testing services. Visual observation techniques were employed to assure compliance with project drawings/specifications, applicable codes, and materials submittals. The following observations were made on site today
Organic unusable soil material was transported from piles located along lots 23 and 24 by two Volvo dump trucks to the transfer pit along the non-structural areas of lot 7 and 8, where a Cat Bulldozer began filling the excavation area.
The site superintendent Morris Pucket (CGU) informed the writer that due to in-climate weather (rainfall.) and site conditions progressively increasing in saturation levels, most construction activity would be focused on general grading (leveling to pad grade) on lots 1, 9, 10, 32 and 33
Lots 1
Lots 32, 33
Transfer Pitt (Lots 7 - 8)