Skip to content

Daily Field Report

Date :07/07/2021
Project No :2021C058
Client Company :Pulte Group
Arrival Time :07/07/2021 08:00
Onsite Hours :00:30
Name of the Project :Parkside at Mason Mill
Project Location :Decatur, GA
Weather :sunny
Departure Time :07/07/2021 08:30
ASEC Technician Name :Andrew McCullough

Observations/Finding

As requested, a ASEC technician was present at the above referenced site for the purpose of conducting a basement wall inspection for lot #216

The wall evaluation was inspected visually for rebar type, spacing, lap distance, cleanliness, ect

The wall preparations appear to be in accordance with Southeast Zone, Date 12/08/2015, Carver & Eddington, NPC plan Number 2468.238-2468.237, Pulti Structural Drawling

by visual inspection, and is ready for concrete placement.

The superintendent has been notified of these findings.

Technician Signature / DateAndrew McCullough, July 7, 2021
Reviewer Name / DateRamchandra Mogulla, August 15, 2021