Daily Field Report

Date :08/25/2021
Project No :2021C073
Client Company :DR Horton West
Arrival Time :08/25/2021 07:30
Onsite Hours :01:30
Name of the Project :Tributary C2A
Project Location :Riverside Parkway, City of Douglasville, GA
Weather :Partly cloudy
Departure Time :08/25/2021 09:00
ASEC Technician Name :Christopher Burrow II

Observations/Finding

The undersigned ASEC Inspector was on site, on the above date, for the purpose of general site monitoring and assessment of contractor and subcontractor activities.

The following are observations that were made at this time:

  • unsuitable material removed from areas mentioned in previous report was being placed in pits made from the mining of structural fill. These pits were measured to be approximately  20’x97’x30’ and 35’x67’x40’.
Technician Signature / DateChristopher Burrow II, August 25, 2021
Reviewer Name / DateRamchandra Mogulla, March 29, 2023