Density Test Report

Date :09/03/2021
Project No :2021C074
Client Company :DR Horton West
Arrival Time :09/03/2021 11:30
Onsite Hours :06:00
Name of the Project :Oakhurst Glen - Ph 4
Project Location :Mallord Drive, South Fulton, GA
Weather :Partly cloudy
Departure Time :09/03/2021 17:30
ASEC Technician Name :Christopher Burrow II

Observations/Finding

Test Date Test Number Moisture Content (%) Dry Density (pcf) Proctor Number Max. Dry Density (pcf) Optimum Moisture (%) Compaction (%) Specified Compaction (%) ASTM Test Method Pass/Fail
09/03/2021 1 16.7 103.3 P-3 103.0 18.1 100.3 95 D2937 Pass
Location : Front center of lot 319, Elv/Depth :13’ below final grade
Comment :
Technician Signature / DateChristopher Burrow II, September 3, 2021
Reviewer Name / DateRamchandra Mogulla, October 13, 2021