Density Test Report

Date :09/04/2021
Project No :2021C074
Client Company :DR Horton West
Arrival Time :09/04/2021 13:00
Onsite Hours :04:00
Name of the Project :Oakhurst Glen - Ph 4
Project Location :Mallord Drive, South Fulton, GA
Weather :Partly cloudy
Departure Time :09/04/2021 17:00
ASEC Technician Name :Christopher Burrow II

Observations/Finding

Test Date Test Number Moisture Content (%) Dry Density (pcf) Proctor Number Max. Dry Density (pcf) Optimum Moisture (%) Compaction (%) Specified Compaction (%) ASTM Test Method Pass/Fail
09/04/2021 1 16.6 101.3 P-3 103.0 18.1 98.3 95 D2937 Pass
Location : Center of lot 316, Elv/Depth :11’ below final grade
Comment :
09/04/2021 2 21.5 98.3 P-3 103.0 18.1 95.4 95 D2937 Pass
Location : Center of lot 315, Elv/Depth :9’below final grade
Comment :
Technician Signature / DateChristopher Burrow II, September 4, 2021
Reviewer Name / DateRamchandra Mogulla, October 13, 2021