- Home
- Daily Field Report Report ID: 34356
- This project is inactive from admin.Download Report
Daily Field Report
Date :10/26/2021
Project No :2021C073
Client Company :DR Horton West
Arrival Time :10/26/2021 07:00
Onsite Hours :01:15
Name of the Project :Tributary C2A
Project Location :Riverside Parkway, City of Douglasville, GA
Weather :Partly cloudy
Departure Time :10/26/2021 08:15
ASEC Technician Name :Christopher Burrow II
Observations/Finding
The undersigned ASEC Inspector was on site, on the above date, for the purpose of general site monitoring and assessment of contractor and subcontractor activities. The following are observations that were made at this time:
-Backfilling pipe mentioned in previous report.
-Continuing placement of lateral along pipe mentioned in previous report.
-Staging and prepping pipe for placement.
Technician Signature / DateChristopher Burrow II, October 26, 2021
Reviewer Name / DateKenneth Mosman, December 09, 2021