Daily Field Report

Date :11/08/2021
Project No :2021C073
Client Company :DR Horton West
Arrival Time :11/08/2021 08:30
Onsite Hours :03:30
Name of the Project :Tributary C2A
Project Location :Riverside Parkway, City of Douglasville, GA
Weather :Partly cloudy
Departure Time :11/08/2021 12:00
ASEC Technician Name :Christopher Burrow II

Observations/Finding

The undersigned ASEC Inspector was on site, on the above date, for the purpose of general site monitoring and assessment of contractor and subcontractor activities. The following are observations that were made at this time:

-Connecting pipes inside of manholes for street drains in area of Lots #416 and 417.

-Excavating along Ancoats Street between approximately Lots #413 through 417 for the street drain.

-Laying pipe between Manhole A1.2 through A1.5 (approximately).

Technician Signature / DateChristopher Burrow II, November 8, 2021
Reviewer Name / DateKenneth Mosman, December 10, 2021