Density Test Report

Date :10/27/2021
Project No :2021C074
Client Company :DR Horton West
Arrival Time :10/27/2021 12:00
Onsite Hours :03:00
Name of the Project :Oakhurst Glen - Ph 4
Project Location :Mallord Drive, South Fulton, GA
Weather :Partly cloudy
Departure Time :10/27/2021 15:00
ASEC Technician Name :Christopher Burrow II

Observations/Finding

Test Date Test Number Moisture Content (%) Dry Density (pcf) Proctor Number Max. Dry Density (pcf) Optimum Moisture (%) Compaction (%) Specified Compaction (%) ASTM Test Method Pass/Fail
10/27/2021 1 11.8 99.6 P-3 103.0 18.1 96.7 95 D2937 Pass
Location : Center of lot 282, Elv/Depth :Final grade
Comment :
Technician Signature / DateChristopher Burrow II, October 27, 2021
Reviewer Name / DateKenneth Mosman, December 04, 2021