Density Test Report

Date :11/10/2021
Project No :2021C073
Client Company :DR Horton West
Arrival Time :11/10/2021 09:30
Onsite Hours :03:00
Name of the Project :Tributary C2A
Project Location :Riverside Parkway, City of Douglasville, GA
Weather :Partly cloudy
Departure Time :11/10/2021 12:30
ASEC Technician Name :Christopher Burrow II

Observations/Finding

Test Date Test Number Moisture Content (%) Dry Density (pcf) Proctor Number Max. Dry Density (pcf) Optimum Moisture (%) Compaction (%) Specified Compaction (%) ASTM Test Method Pass/Fail
11/10/2021 1 18 100.3 P-01 93.9 22.6 106.8 95 D6938 Pass
Location : Storm Drain pipe behind lot 442, Elv/Depth :Final grade
Comment : Gauge Serial No. :38069
11/10/2021 2 15.4 108.1 P-01 93.9 22.6 115.1 95 D6938 Pass
Location : Storm drain pipe behind lot 443, Elv/Depth :Final grade
Comment : Gauge Serial No. :38069
Technician Signature / DateChristopher Burrow II, November 10, 2021
Reviewer Name / DateKenneth Mosman, December 16, 2021