Skip to content

Daily Field Report

Date :11/11/2021
Project No :2021C074
Client Company :DR Horton West
Arrival Time :11/11/2021 14:30
Onsite Hours :02:30
Name of the Project :Oakhurst Glen - Ph 4
Project Location :Mallord Drive, South Fulton, GA
Weather :Partly Cloudy
Departure Time :11/11/2021 17:00
ASEC Technician Name :Christopher Burrow II

Observations/Finding

The undersigned ASEC Inspector was on site, on the above date, for the purpose of general site monitoring and assessment of contractor and subcontractor activities. The following are observations that were made at this time:

-Continuing pipe laying in the area of lots 310 through 314.

-Placed fill on lots 335 through 337 but was not compacted at the time of site visit so no density tests were taken.

-Rock Breaking continued on site.

-Continued moving rocks into excavated pits.

Technician Signature / DateChristopher Burrow II, November 11, 2021
Reviewer Name / DateKenneth Mosman, December 06, 2021