Daily Field Report

Date :11/17/2021
Project No :2021C082
Client Company :CCG Constructors LLC (Century)
Arrival Time :11/17/2021 11:30
Onsite Hours :02:30
Name of the Project :Estates at Old Friendship
Project Location :Buford, GA
Weather :Partly cloudy
Departure Time :11/17/2021 14:00
ASEC Technician Name :Christopher Burrow II

Observations/Finding

The undersigned ASEC Inspector was on site, on the above date, for the purpose of general site monitoring and assessment of contractor and subcontractor activities. The following are observations that were made at this time:

-Excavating cut areas on road to bring them to grade.

-Undercut area in road approximately 20’x40’x3’ where unsuitable soil was discovered.

-Prepping roadway for fill tomorrow.

Technician Signature / DateChristopher Burrow II, November 17, 2021
Reviewer Name / DateKenneth Mosman, February 16, 2023