Daily Field Report

Date :12/21/2021
Project No :2021C060
Client Company :Pulte Group
Arrival Time :12/06/2021 15:00
Onsite Hours :01:00
Name of the Project :Suncity - Peachtree
Project Location :Griffin, GA
Weather :cloudy
Departure Time :12/06/2021 16:00
ASEC Technician Name :Russell Hendrix

Observations/Finding

The site was visited by the undersigned AS Engineering and Consulting (ASEC) representative for the purpose of providing quality control inspection and testing services. Visual observation techniques were employed to assure compliance with project drawings/specifications, applicable codes, and materials submittals. The following observations were made on site today:

A request was made to inspect Lot #101 in the “Passport” section of the development.  All rebar was installed to IBC code for size, spacing and quantity.  The area was probed and a DCP was completed.  The foundation bearing pressure was found to be suitable for concrete placement.  Please see the attached report.

DCP TEST DATA SHEET
                         
Project Name: Suncity   Date: 12/06/21
Project Number: 2021c060   Technician: Russ Hendrix
Project Location: Griffin
     
                         
DCP LOCATION:
Lot #, North/South/Center etc
Lot 101   DCP LOCATION:
Lot #, North/South/Center etc
 
     
                         
Depth
(feet)
Set
2″
N
1.75″
Description   Depth
(feet)
Set
2″
N
1.75″
Description
1   10 Red silty fine sand   1      
2   12 Red silty fine sand   2      
3   10 Red silty fine sand   3      
4   10 Red silty fine sand   4      
5         5      
6         6      
7         7      
8         8      
9         9      
10         10      
                         
                         
DCP LOCATION:
Lot #, North/South/Center etc
    DCP LOCATION:
Lot #, North/South/Center etc
 
     
                         
Depth
(feet)
Set
2″
N
1.75″
Description   Depth
(feet)
Set
2″
N
1.75″
Description
1         1      
2         2      
3         3      
4         4      
5         5      
6         6      
7         7      
8         8      
9         9      
10         10      
                         
NOTES:  
 
 

 

Technician Signature / DateRussell Hendrix, December 21, 2021
Reviewer Name / DateKenneth Mosman, December 21, 2021