Daily Field Report

Date :01/27/2021
Project No :2021C060
Client Company :Pulte Group
Arrival Time :01/27/2021 04:00
Onsite Hours :00:45
Name of the Project :Suncity - Peachtree
Project Location :Griffin, GA
Weather :
Departure Time :01/27/2021 04:45
ASEC Technician Name :Jamal Geathers

Observations/Finding

The site was visited by the undersigned AS Engineering and Consulting (ASEC) representative for the purpose of providing quality control inspection and testing services. Visual observation techniques were employed to verify compliance with project drawings/specifications, applicable codes, and materials submittals.

The ASEC representative performed foundation bearing tests in the below referenced footing areas.  All referenced footings were found to meet the job specification for a soil bearing pressure of 2,500 psf.

A reinforcing steel inspection was performed on the following locations: (Lots #10 Pod 15).  Reinforcing steel was observed to meet job specifications for required size, spacing, lap and cover. No discrepancies were noted.

If foundation soil become wet prior to concrete placement, it should be reevaluated by a geotechnical engineer or qualified soils technician. All loose fall-in soils or debris should be removed from foundations prior to concrete placement.

 

DCP LOCATION:
Lot #, North/South/Center etc
Lot 10 back of lot (offset) DCP LOCATION:
Lot #, North/South/Center etc
lot 10 back of lot
Depth
(feet)
Set
2″
N
1.75″
Description Depth
(feet)
Set
2″
N
1.75″
Description
1 6 11 1 6 13
2 6 13 2 6 12
3 6 AR auger refusal 3 6 11
4 6 4 6 16
Technician Signature / DateJamal Geathers, January 27, 2021