Daily Field Report

Date :03/03/2022
Project No :2021C060
Client Company :Pulte Group
Arrival Time :03/03/2022 08:30
Onsite Hours :01:00
Name of the Project :Suncity - Peachtree
Project Location :Griffin, GA
Weather :53
Departure Time :03/03/2022 09:30
ASEC Technician Name :Jamal Geathers

Observations/Finding

The site was visited by the undersigned AS Engineering and Consulting (ASEC) representative for the purpose of providing quality control inspection and testing services. Visual observation techniques were employed to verify compliance with project drawings/specifications, applicable codes, and materials submittals.

The ASEC representative performed foundation bearing tests in the below referenced footing areas.  All referenced footings were found to meet the job specification for a soil bearing pressure of 2,000 psf.

A reinforcing steel inspection was performed on the following locations: (Lots #112 & #5).  Reinforcing steel was observed to meet job specifications for required size, spacing and quantity. No discrepancies were noted.

If foundation soils become wet prior to concrete placement, they should be reevaluated by a geotechnical engineer or qualified soils technician. All loose soils or debris should be removed from foundations prior to concrete placement.

 

DCP LOCATION:
Lot #, North/South/Center etc
112 DCP LOCATION:
Lot #, North/South/Center etc
5
Depth
(feet)
Set
2″
N
1.75″
Description Depth
(feet)
Set
2″
N
1.75″
Description
1 5 13 red orange soil type 1 5 8
2 5 12 2 5 12
3 5 12 3 5 7
4 5 11 4 5 18+
Technician Signature / DateJamal Geathers, March 3, 2022
Reviewer Name / DateKenneth Mosman, March 19, 2022