Daily Field Report
Observations/Finding
The site was visited by the undersigned AS Engineering and Consulting (ASEC) representative for the purpose of providing quality control inspection and testing services. Visual observation techniques were employed to verify compliance with project drawings/specifications, applicable codes, and materials submittals.
A reinforcing steel inspection was performed on the following locations: (Lot #37). Reinforcing steel was observed to meet job specifications for required size, spacing, and quantity. No discrepancies were noted.
If foundation soils become wet prior to concrete placement, they should be reevaluated by a geotechnical engineer or qualified soils technician. All loose and soft soils or debris should be removed from foundations prior to concrete placement.
Spoke to Ronald Moore about standing water in the footing and on top of the vapor barrier.