Daily Field Report

Date :04/15/2022
Project No :2022C128
Client Company :Century
Arrival Time :04/08/2022
Onsite Hours :
Name of the Project :Sidney Square, Flowery Branch
Project Location :Flowery Branch
Weather :45 sunny
Departure Time :04/08/2022
ASEC Technician Name :Russell Hendrix

Observations/Finding

The site was visited by the undersigned AS Engineering and Consulting (ASEC) representative for the purpose of providing quality control inspection and testing services. Visual observation techniques were employed to assure compliance with project drawings/specifications, applicable codes, and materials submittals. The following observations were made on site today:

Upon arrival it was observed that the area excavated for the headwall at X1 had water intrude overnight with a depth of over 2 inches.  A pump was used to remove the in-situ water.  The remediation from the previous day was continued with the addition of the remaining surge stone.  No further observations were made on this date.

Technician Signature / DateRussell Hendrix, April 15, 2022
Reviewer Name / DateKenneth Mosman, April 24, 2022