Daily Field Report

Date :06/10/2022
Project No :2020C007
Client Company :Pulte Group
Arrival Time :06/10/2022 7:00
Onsite Hours :01:00
Name of the Project :Winslow at Brookstone
Project Location :6156 Collins Road, Acworth, GA 30101
Weather :Sunny
Departure Time :06/10/2022 8:00
ASEC Technician Name :Vidal Dias

Observations/Finding

On June 9th & 10, 2022, Vidal Dias of AS Engineering and Consulting, LLC (ASEC) visited the site at the contractor’s request to observe footing excavations for the shallow foundations for Lot #48. On June 9th the footings were found to contain loose, wet soils and were unsuitable for concrete placement. Our representative returned to the site on June 10th and hand augering exposed stiff residual silty fine sands. Soils were found to be acceptable to support the proposed one-story structure for an allowable soil bearing pressure of 2000 psf. Auger refusal was encountered at three feet. Concrete should be placed before the onset of inclement weather. If excavations become wet and/or softened prior to concrete placement, ASEC should be contacted to re-evaluate the foundation soils.

 

 

 

Project Name: Winslow at Brookstone Date: 6/10/2022
Project Number: Technician: Vidal Dias
Project Location:
DCP LOCATION:
Lot #, North/South/Center etc
 Lot 48 DCP LOCATION:
Lot #, North/South/Center etc
Depth
(feet)
Set
2″
N
1.75″
Description Depth
(feet)
Set
2″
N
1.75″
Description
1 16 Tan, Silty fine to medium SAND 1
2 17 Tan, Silty fine to medium SAND 2
3 AR 3
4 4
5 5
6 6
7 7
8 8
9 9
10 10
Technician Signature / DateVidal Dias, June 10, 2022
Reviewer Name / DateKenneth Mosman, June 19, 2022