Skip to content

Daily Field Report

Date :06/14/2022
Project No :2021C060
Client Company :Pulte Group
Arrival Time :06/14/2022 08:00
Onsite Hours :04:00
Name of the Project :Suncity - Peachtree
Project Location :Griffin, GA
Weather :Sunny
Departure Time :06/14/2022 12:00
ASEC Technician Name :Vidal Dias

Observations/Finding

Our AS Engineering and Consulting, LLC (ASEC) representative visited the site at the contractor’s request to visually inspect footing excavations for shallow footings for Lots #21, 78, 63, and 16.  Our hand auguring/probing exposed stiff residual silty fine sands. However, loose soils were encountered around the area where pipes were exposed. We recommended that additional reinforcing steel be added to these areas.  Soils were found to be acceptable to support the proposed one-story structure for an allowable soil bearing pressure of 2000 psf. Concrete should be placed before the onset of inclement weather. If excavations are become wet and/or soft, ASEC should return to the site to re-evaluate the foundations soils.

Technician Signature / DateVidal Dias, June 14, 2022
Reviewer Name / DateKenneth Mosman, June 19, 2022