Density Test Report

Date :05/04/2022
Project No :2022C135
Client Company :Mark Spain
Arrival Time :05/04/2022 08:00
Onsite Hours :9:30
Name of the Project : Barnett Shoals Road Development
Project Location :Watkinsville
Weather :
Departure Time :05/04/2022 17:30
ASEC Technician Name :Rasheen Biggins

Observations/Finding

Test Date Test Number Moisture Content (%) Dry Density (pcf) Proctor Number Max. Dry Density (pcf) Optimum Moisture (%) Compaction (%) Specified Compaction (%) ASTM Test Method Pass/Fail
05/04/2022 1 22.9 105.3 P-1 97.3 23.7 108.2 95 D6938 Pass
Location : within the dam area, Elv/Depth :below finished grade
Comment : Soils placed in this area may be a mixture of different moisture-density relationships (proctors) Gauge Serial No. :38069
05/04/2022 2 23.4 105.2 P-1 97.3 23.7 108.1 95 D6938 Pass
Location : within the dam area, Elv/Depth :below finished grade
Comment : Soils placed in this area may be a mixture of different moisture-density relationships (proctors) Gauge Serial No. :38069
05/04/2022 3 20.0 108.5 P-1 97.3 23.7 111.5 95 D6938 Pass
Location : within the dam area, Elv/Depth :below finished grade
Comment : Soils placed in this area may be a mixture of different moisture-density relationships (proctors) Gauge Serial No. :38069
05/04/2022 4 26.2 102.2 P-1 97.3 23.7 105.0 95 D6938 Pass
Location : within the dam area, Elv/Depth :below finished grade
Comment : Soils placed in this area may be a mixture of different moisture-density relationships (proctors) Gauge Serial No. :38069
05/04/2022 5 20.0 103.0 P-1 97.3 23.7 105.9 26.2 D6938 Pass
Location : within the dam area, Elv/Depth :below finished grade
Comment : Soils placed in this area may be a mixture of different moisture-density relationships (proctors) Gauge Serial No. :38069
Technician Signature / DateRasheen Biggins, May 4, 2022
Reviewer Name / DateKenneth Mosman, July 04, 2022