Daily Field Report

Date :04/22/2022
Project No :2021C078
Client Company :CCG Constructors LLC (Century)
Arrival Time :04/22/2022 14:00
Onsite Hours :04:00
Name of the Project :Pickens Landing Development
Project Location :Dacula, GA
Weather :78
Departure Time :04/22/2022 18:00
ASEC Technician Name :Rasheen Biggins

Observations/Finding

Our AS Engineering and Consulting (ASEC) representative visited the site for the purpose of providing quality control inspection and testing services. Visual observation techniques were employed to assure compliance with project drawings/specifications, applicable codes, and materials submittals. The following observations were made on site today.

Upon arrival our representative found that work was already in progress. The contractor continued placing fill around the A11 structure with a Komatsu 39px bulldozer (soil was bought by 1 Cat dump truck) and compacted with a Sakai cp-11 Caterpillar compactor. Each lift placed was approximately 10 inches in thickness. Density tests were performed using a Troxler 3430 nuke gauge #38069.   Test results were reported to the contractor. Following several failing density tests, our representative contacted Ram Mogulla, P.E. of ASEC for guidance.  Mr. Mogulla recommended a proof-roll be performed in this area to test stability. The proof-roll found the surficial soils to be stable and the contractor continued with the placement of an additional lift.

Technician Signature / DateRasheen Biggins, April 22, 2022
Reviewer Name / DateKenneth Mosman, July 31, 2022