- Home
- Daily Field Report Report ID: 54219
- This project is inactive from admin.Download Report
Daily Field Report
Date :07/12/2022
Project No :
Client Company :DRH
Arrival Time :07/12/2022 07:30
Onsite Hours :07:00
Name of the Project :Summerwind, PH II
Project Location :Dacula
Weather :Cloudy
Departure Time :07/12/2022 14:30
ASEC Technician Name :Jared Barrios
Observations/Finding
Our ASEC representatives were on-site to perform Dynamic Cone Penetrometer (DCP) testing on the previously constructed lots for the Summerwind Phase 2 property. Results will be submitted in a separate, final report.
Technician Signature / DateJared Barrios, July 12, 2022
Reviewer Name / DateKenneth Mosman, July 20, 2022