Skip to content

Daily Field Report

Date :07/13/2022
Project No :
Client Company :DRH
Arrival Time :07/13/2022 08:00
Onsite Hours :06:30
Name of the Project :Summerwind, PH II
Project Location :Dacula
Weather :Cloudy and rainy
Departure Time :07/13/2022 14:30
ASEC Technician Name :Jared Barrios

Observations/Finding

Our ASEC representatives arrived on site to being performing Dynamic Cone Penetrometer (DCP) testing for the prepared lots on the Summerwind Phase 2 property.  Results of DCP testing will be submitted in a final report at a later date once all work is completed.

Technician Signature / DateJared Barrios, July 13, 2022
Reviewer Name / DateKenneth Mosman, July 20, 2022