Daily Field Report

Date :08/24/2022
Project No :2021C002
Client Company :CW Matthews
Arrival Time :08/24/2022 19:30
Onsite Hours :06:45
Name of the Project :Runway 9L End Around Taxiway
Project Location :HJAIA
Weather :Cloudy
Departure Time :08/25/2022 02:15
ASEC Technician Name :Jared Barrios

Observations/Finding

The ASEC representative arrived on site at around 7:30 pm. The team of technicians were able to complete at least 3 tests with the first test being the initial test. The team of technicians were able to construct 2 sets of beams. I departed at around 2:15 am.

Technician Signature / DateJared Barrios, August 24, 2022
Reviewer Name / DateRamchandra Mogulla, October 03, 2022